Completion time - clauses 2,6,22 - HIA Agreement. Can you explain what this means?
Completion time is the period we have to finish your project, from when construction begins to practical completion. It is counted in working days, not calendar days.
The count starts 15 days after we receive Building Approval (the stamped plans) from the private building certifier. It runs until practical completion.
Practical completion means the building works have reached the stage where we certify they have been completed in accordance with the contract, except for minor omissions. Where applicable, it also means we have done all that we are required to do under the contract to enable a certificate of occupancy to be obtained. It is formally reached when you and we sign the Customer Project Walkthrough.
The completion time can be extended. Only working days count when a delay happens. Delays in finalising your inclusions choices also extend the completion time. When a delay happens, we send you a time delay letter. It states the date sent, the number of working days delayed and the reason.
Our time guarantee: once all approvals are in place and construction is ready to start, we work to finish within the timeframe in your signed HIA agreement. If we do not meet it, we will compensate you at $250 per day (which is $1,750 a week), or provide accommodation in a 5-star hotel, until your project is complete.
The guarantee is subject to reasonable conditions. These include changes you request that affect design, selections or scope, weather and other delays outside our control, restricted or delayed access to the site, and authority, utility or approval delays outside our control. The guarantee is outlined in your project proposal and reflected in Schedule 1 of your HIA agreement. Please read the full terms with your HIA agreement.
CGFB-Q-0184 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?