Can you submit a DA/entities referral without implementing the contour and detail survey into the project plans?
What the planning process requires
A Development Application (DA) goes through a completeness check before it is accepted for assessment. A current contour and detail survey is needed for that check. Without it, the application is likely to fail the check. If it fails, it is not lodged for public notification or assessment.
_______
How we handle it
We do not lodge a DA without the survey. A survey certificate alone is not enough if the project plans do not show the survey. The plans should be drawn with the survey included, so the plans and the survey match. Ideally the survey is no older than 12 months. A survey older than 12 months is likely to be rejected by the Planning Department and/or the certifier. If you do not have a current survey, we arrange one for you.
CGFB-Q-0495 · last reviewed 24 November 2026