Can you provide a DA timeline?
The time for DAs, or Development Applications, depends somewhat on the type of work planned and how complex the development is. Generally, you can expect planning approvals to take 8-10 months.
Preparation of DA documents – up to 1 month, depending on whether pre-application advice is sought.
Initial check of document completeness – 10-15 working days.
DA Lodgement (including Public Notification, entity referral, assessment by the Territory Planning Authority and pre-decision advice) – 90 working day statutory timeframe.