Can we occupy the structure before a COU is issued?
No. It is against the law to occupy or use a building, or part of a building, until a Certificate of Occupancy and Use (COU) has been issued for the purpose it will be used for. This includes using an existing building for a different purpose.
A certificate can be issued for a completed part of a building if that part meets the requirements. The part without a certificate still cannot be occupied.
Reference: Building Act 2004 (A2004-11).
How we handle it: after the project walkthrough, we gather the installation and compliance certificates your certifier needs. Ideally the certifier receives the application about a week after the walkthrough. The certifier issues the Certificate of Completion and then lodges the COU application, because only your appointed certifier can do this. On average, the government issues the COU about three weeks after handover, subject to government processes. Please do not move in or rent the property until it is issued.
CGFB-Q-0710 · last reviewed 24 November 2026